Welcome to Nitin’s Blog…

Here you will find:

Snapshot of my experience in planning, claims and applied research over the last 14 years.

Compilation of my research in the area of positive safety for continual improvement in the civil/construction industry

Platform to share my experience and work towards better planning practices with other industry professionals.

Please click "Enter" to Read more

ENTER

Monday 23 July 2012

Level Definitions for programme


                                                  Core Scheduling Papers: #6

Schedule Levels – Major Projects

Level 1 Schedule Executive Summary, also called a Project Master Schedule (PMS). This is a major milestone type of schedule; usually only one page, it highlights major project activities, milestones, and key deliverables for the whole project. It is used to summarise the project schedule in reports and other documents when a more detailed schedule is not required.

Frequently developed by the ‘client’ as part of its initial feasibility studies for the project and then maintained by the contractor. Can be used to integrate multiple contractors / multiple project schedules into an overall program schedule.
Level 2 Schedule Management Summary, also called a Summary Master Schedule (SMS). Maintained as a summarisation of the Level 3 Project Coordination Schedule(s). It depicts the overall project broken down into its major components by area and is used for higher-level management reporting.

Frequently developed by the ‘client’ as part of its commitment planning for the project and then maintained by the contractor. Can be used to integrate multiple contractors / multiple project schedules for the overall control of a program. It will include the Level 1 information expanded to show activities by area or major item of capital equipment.
Level 3 Schedule Project Coordination Schedule (PCS) also called a Publication Schedule. Initially developed as an integrated CPM overview of the project, the Level 3 schedule is then maintained as an integrated rollup or summary of the Level 4 schedule activities for reporting status to senior management and to report monthly status to major clients, etc. The schedule consists of a set of integrated Level 4 schedules based on Critical Path Methodology (CPM) and is developed with detailed input from the project management team. Usually developed by the ‘main contractor’ as part of its tendering process for the project or by the project team during the initial phases of planning.

The Level 3 schedule spans the whole of the project and is used to support the monthly report. It includes all major milestones, major elements of design, engineering, procurement, construction, testing, commissioning and/or start-up. If the Level 4 schedules are primarily developed by trade/sub-contractors, during the initial phases of the project the Level 3 schedule provides the schedule framework and constraints used by the subcontractors to develop their tenders. During the execution phase of the project this schedule defines the overall critical path and is the primary coordination tool for the overall project.
Level 4 Schedule Execution Schedule, also called a Project Working Level Schedule. Level 4 is the detailed working level schedule, where each schedule is an expansion of part of a Level 3 schedule, and is established within the integrated project schedule. This is the key working level CPM schedule displaying the activities to be accomplished by the project workforce and is required for every project. The dates generated by the schedule activities represent the anticipated start and completion of work required to complete the project. If there is no ‘Level 3’ schedule, activities in future months/years may be summary in nature but still provide approximate start and completion dates for major pieces of work (this is called ‘rolling wave scheduling’).

Developed by the ‘contractor’, ‘subcontractor’ (trade contractor), or the project team prior to commencing work on the project execution, or work in a phase or area of the project. The Level 4 schedule may be for the whole of the project or a part of the project depending on the size of the project and complexity of the work. A critical factor is keeping each ‘Level 4’ schedule to a sensible size that can be easily managed, updated, validated, etc. ‘Level 4’ schedules may be for major sections of the work or for discrete processes such as a ‘Design Schedule’, ‘Procurement schedule’ and/or a ‘Commissioning Schedule’. Generally, the ‘Level 4’ schedule represents the area of authority of a section manager or engineer, so one manager is responsible for all of the work in the schedule. Activities are generally over a week in duration (depending on the nature of the project). Where used, short term ‘look ahead’ are produced from this level; typically ‘Three Week Look-ahead’ schedules are updated every two weeks.

Level 5 Schedule Detail Schedule.
The further breakdown of the activities of a Level 4 Schedule. A short term schedule used to map out the detailed tasks needed to coordinate day to day work in specific areas.


Blog Contributor: Karthik T. (Planner, UK)


© Practical PM Pty Ltd, 2010 www.mosaicprojects.com.au/Planning.html